How should a drip edge be installed at the eave?

Study for the B3/61 Contractor Trade Exam. Use our comprehensive quizzes with flashcards and multiple-choice questions, each complete with hints and explanations. Be confident and well-prepared for your exam day!

Multiple Choice

How should a drip edge be installed at the eave?

Explanation:
Water management at the eave depends on the layering order of the drip edge and the underlayment. The drip edge should be placed beneath the underlayment so that when the underlayment is applied, it overlaps and covers the edge. This creates a smooth, protected edge that directs water into the gutter and prevents moisture from seeping behind the edge into the roof deck or fascia. Installing the drip edge before the underlayment helps seal the eave and maintain a durable, water-shedding surface.

Water management at the eave depends on the layering order of the drip edge and the underlayment. The drip edge should be placed beneath the underlayment so that when the underlayment is applied, it overlaps and covers the edge. This creates a smooth, protected edge that directs water into the gutter and prevents moisture from seeping behind the edge into the roof deck or fascia. Installing the drip edge before the underlayment helps seal the eave and maintain a durable, water-shedding surface.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy