Floating and troweling concrete too early in the curing process can cause which of the following?

Study for the B3/61 Contractor Trade Exam. Use our comprehensive quizzes with flashcards and multiple-choice questions, each complete with hints and explanations. Be confident and well-prepared for your exam day!

Multiple Choice

Floating and troweling concrete too early in the curing process can cause which of the following?

Explanation:
Finishing a concrete surface too soon interacts with bleed water. As concrete sets, some water separates and rises to the surface. If you float or trowel before this bleed water settles, the finishing tools push that water up and carry some cement paste with it, creating a thin, water-rich surface layer (laitance). That excessive water on the surface weakens the top layer and leads to problems like dusting and scaling after curing. The other effects described (like moving aggregates or water ending up at the bottom) aren’t caused by finishing too early, so the right consequence of premature finishing is the excessive surface water.

Finishing a concrete surface too soon interacts with bleed water. As concrete sets, some water separates and rises to the surface. If you float or trowel before this bleed water settles, the finishing tools push that water up and carry some cement paste with it, creating a thin, water-rich surface layer (laitance). That excessive water on the surface weakens the top layer and leads to problems like dusting and scaling after curing. The other effects described (like moving aggregates or water ending up at the bottom) aren’t caused by finishing too early, so the right consequence of premature finishing is the excessive surface water.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy